When should a lead exposure-related hazard assessment be conducted?

  1. At the start of the project

  2. Before any employee is assigned to lead-related work

  3. Both A and B

  4. Only if exposure levels exceed the PEL

The correct answer is: Both A and B

Conducting a lead exposure-related hazard assessment is crucial for ensuring the safety of employees who may come into contact with lead-containing materials. The assessment should be performed at the start of a project to identify potential lead hazards and to establish appropriate control measures. This proactive approach ensures that any risks are mitigated before work begins, promoting a safe working environment from the outset. Additionally, performing the assessment before any employee is assigned to lead-related work is equally essential. It safeguards employees by ensuring they are not exposed to lead hazards without prior knowledge and protective measures being put into place. This means that individuals can be adequately informed about the risks and trained on safety protocols before engaging in any potentially hazardous tasks. Overall, both timing considerations are integral to maintaining workplace safety and adhering to regulatory requirements surrounding lead exposure. This comprehensive assessment helps to minimize health risks associated with lead exposure and promotes informed decision-making regarding employee assignments and protective measures.